Phase 2A of the Matibi Mission Hospital Operating Theatre renovation delivers core structural, flooring, tiling, painting, sanitary, and door installations to restore Theatre 1, Theatre 2, and all associated support areas to full surgical functionality and modern healthcare standards.
Project Context
The theatre renovation is a multi-phase undertaking. Phase 1 completed initial minor structural repairs, preliminary plumbing and electrical upgrades, and basic internal finishing. Phase 2A now concentrates on the critical core works — structural strengthening, medical-grade flooring, tiling, hospital-grade painting, sanitary installations, and surgical door upgrades — that will leave the theatre in a fully functional state meeting infection control and surgical safety standards.
Scope of Works
- •Structural underpinning — engineering-approved strengthening of theatre foundations
- •Surgical-grade vinyl flooring — 120 m² across Theatre 1, Theatre 2, and Sterilisation Room
- •Ceiling reinstallation — 170 m² moisture-resistant panels
- •Hospital-grade gloss paint — walls and ceilings (250 m²) and sluice room (400 m²)
- •Doors — hermetic airtight surgical swing door (scrub-to-theatre) and teak double main theatre doors
- •Sanitary installations — 2 surgical elbow-operated scrub sinks, 1 stainless steel sluice sink, 1 toilet
- •Water purification system — ensuring sterile water supply for surgical procedures
Detailed Budget (Bill of Quantities)
- •Surgical-grade vinyl flooring (120 m²): $4,800
- •Hermetic airtight surgical swing door: $6,266
- •Structural underpinning: $7,700
- •Hospital-grade gloss paint — theatre walls & ceilings (250 m²): $3,600
- •Moisture-resistant ceiling reinstallation (170 m²): $2,040
- •Teak double door with hospital-grade hardware: $960
- •Double stainless steel sluice sink: $400
- •Gloss paint — sluice room walls & ceiling (400 m²): $4,800
- •Toilet seat and cistern: $250
- •Water purification system: $4,700
- •Surgical elbow-operated scrub sinks (×2): $2,400
- •Site protection, waste removal and commissioning: $1,100
Grand Total: USD $39,016
Implementation Timeline
- •Structural works: 6 weeks
- •Flooring installation: 3 weeks (following structural completion)
- •Tiling works: 4 weeks
- •Internal painting: 2 weeks
- •Sanitary installation and doors: 3 weeks
Total duration: ~10–12 weeks (activities overlap where possible)
Implemented in partnership with Matibi Mission Hospital, the Ministry of Health and Child Welfare Zimbabwe, Mwenezi District Council, and the Ministry of Public Works.